The Scheme cost €114m.
A major drainage scheme project in Westmeath is nearing completion after two years of works.
The €114m Athlone Scheme is expected to see waste flows turned into the new sewer network by October.

Uisce Eireann's latest update details a number of objectives that have been met over the last number of weeks.
All tunnelling is now finished with reinstatement works underway across the town.
Works along The Quays have also been completed while the construction of the Golden Island pumping station shaft construction is done with mechanical and electrical installations still progressing.
The Coosan West Pumping Station is also now in operation, providing enhanced wastewater management capacity for the area.
The main works taking place over the next number of weeks involve cross connections between the existing and the new network.
Midlands 103 has received confirmation the Strand Carpark will re-open in October.
At that stage Athlone's Main Drainage project team will begin will public realm enhancements on Custume Place.
Laois TD Warns Drug Debts Are Being Collected Through Fear And Intimidation
Bottle And Can Returns Raise Over €300K For Charities This Summer
Lifeboat Press Officer Issues Safety Warning Ahead Of Bank Holiday Weekend
Midlands MEP Slams ‘Fantasy Football’ Economics Over Future of CAP
Offaly Traditional Musician Donal Lunny Passes Away
"A Slap In The Face"- Westmeath Graduate Nurse Pushes For Answers On Job Contract
Westmeath Community Celebrating Tidy Towns 2026 Victory
Westmeath Man Set To Compete In Dublin City Marathon For The First Time